We did get some dramatic moments near the end of the day, though, when they raised the two dormers. Check it out.
Tuesday, September 30, 2008
Framing-Sunday
Framing-Saturday
About 1 p.m., clouds rolled in and we heard a loud crack of thunder. Gerald and I said, "thunder," and we could hear the workers say the same thing in unison, only in Spanish.
A few rain drops fell, and I thought it would pass. Instead, the rain was hard enough to run me inside. Pretty soon, it was pouring. The construction crew took cover in the garage. It probably rained for the better part of an hour.
At the end, the campsite was a soggy mess, but the workers got back to work. J.C. Campbell went to work digging a trench for a pipe to bring the well water into the house.
When we got back, the whole driveway was torn up and muddy. We changed our clothes for the party and had to hike through rocks and bushes to get to the truck. That wasn't so bad. What was worse was that we had to do it again coming back--in the dark, with only a penlight flashlight.
The construction crew was gone by then, but J.C. worked until well past dark.
Framing-Friday
Twelve, 2x12's appeared to be missing, but were later found. Then we realized the materials for the loft had not been ordered at all. We were also short of sheeting material. Gerald spent most of the morning on the phone with Paul and various suppliers to try to round up the missing materials and get them delivered. Jason needed the 2x12s for the loft by the morning. Gerald eventually arranged for Old Santa Fe Lumber to deliver them that night. The situation got very tense. Gerald wasn't happy.
On our way out, we saw these horses. They were outside the ranch gate but before the highway.
Paul had talked to the Yavapai County Planning Office about the changes to the plans. The person he spoke with said we just needed to bring in our stamped plans and they could approve the changes in a few minutes. When we got there, they told Gerald they needed two sets of plans and that it would take 6 or 7 hours once they had them. The rules are the rules, they said.
Gerald called Paul, who remembered who he had spoken with. Once Gerald got to the right person, and he remembered having that conversation, it took just a few minutes to approve the changes.
Materials delivery
Monday, September 22, 2008
The plot thickens
This building project is starting to feel like it has more plot twists than a Bond movie.
While we were waiting for the revised bid from Dennis, our original contractor called with a plan to salvage his original contract. The job would still be done under the terms we had agreed to, but he wouldn't be here to oversee it. He had a large crew that could start on Friday and finish framing the house in two consecutive weekends.
The plan had certain merits. We wouldn't have to figure out what to do with the back hoe, as it would be part of Paul's compensation. It would also mean we would have to come up with less additional money. And that would mean we could do more work than we had planned, like the siding or the electrical work.
That part became important after our financing finally fell apart. After jumping through all the hoops for Chase Bank, Wells Fargo refused to subordinate their loan. Which means we're back to paying as we go.
While we were mulling all this over, Dennis's bid came in considerably higher than his original estimate. That made it an easy decision.
Paul e-mailed a contract and we accepted, then Gerald went to work to change the materials delivery to coincide with the schedule of our new crew.
Saturday, September 20, 2008
Starting over
We got some disappointing news this week. Our builder, Paul Russell, called to say he would not be able to come back from Missouri to finish our job. His new employer told him that if he took a week or two off, he wouldn't have a job to come back to. So we were back to square one.
Gerald spent a lot of time trying to line up another contractor and got a referral from Wayne Ohland, a commercial builder and neighbor. Wayne built the addition on our primary home. He and his wife also split the original 36-acre parcel with us, so they own the 18 acres adjacent to our parcel at Ruger Ranch as well.
Gerald talked to the contractor, Dennis, and arranged for him to meet us up at the land on Saturday.
We arrived at the land on Friday. After setting up camp, we went to work rolling the final coat of masonry sealer, so J.C. Campbell could start backfilling on Saturday.
J.C. and the new contractor arrived about the same time, around 8 a.m. Gerald put them to work helping to unload a jetted tub we had bought for $160 at Stardust, a Habitat for Humanity store.
The meeting with Dennis went well, though the land was farther from his home in Queen Creek than he anticipated, and he said he had to go home to crunch some new numbers. Still, we felt fairly confident that this would all work out, and made plans to leave a day early with the expectation that we would need to come back on Monday to be on-site for a Tuesday materials delivery.
Sunday, September 7, 2008
Chili and roping
We spent Saturday sealing the rest of the masonry, which is as photogenic as it sounds.
On Saturday afternoon, we joined the Stowes for a chili and roping party. I'm happy to say that both Gerald and I roped our respective targets and were allowed to proceed to the serving line.
On Sunday morning we got about five rain drops, but the clouds were breaking up by the time I got up for my hike.
My thighs were sore from all the up and down from painting on Saturday, but Gerald felt fine. I wanted to know how it was that I exercise everyday, yet I'm sore and he isn't. He attributed it to the scotch keeping him limber. "You train your way, I'll train mine," he said.
I had to admit he had me beat.
Monday, September 1, 2008
The View
Labor Day Weekend
We headed up to the land on Thursday of Labor Day weekend because the garage door was scheduled to be installed at 9:30 on Friday morning.
The theory behind the device is that the gnats only drive Gerald crazy when they buzz around his ears. This worked better than his previous gnat protection device, which consisted of torn pieces of dryer sheets hung over his ears. He did not want me to photograph that one, either.
I didn't like this as well. He couldn't hear the gnats, but he couldn't hear me either, or at least so he said.
The garage door installer arrived around 10 a.m. and worked all day. It was nearly 5 p.m. by the time he was finished, but the garage door was installed.
Saturday morning, J.C. Campbell and a helper he recruited from the Bagdad mine came to work on the floor. By 10 a.m. they had installed all the floor joists over the garage.
Labels:
garage door,
gnat protection,
joists,
sub-floor
Subscribe to:
Comments (Atom)