Monday, October 6, 2008

Week 2 Framing

It was cold on Saturday. Just the week before, the temperatures were in the mid-80s. On Saturday, it was cloudy and about 60 for most of the day.

The highlights of the day involved the crane. We took advantage of it being there to put our fireplace upstairs and drop in our jetted tub.







The crane also set in place a log we're using as a post upstairs.












The crew built a temporary structure to support it. That's Jason, the crew foreman.












Next, went the beams to support the roof.